Skip to content

19 — Release Plan

1. Purpose

Versioning, branching, the release process, and the version-by-version maturity map. Upstream authority: Charter §7.5 (SemVer, 0.x rules, 1.0 freeze), §9.1 (scorecard), §12 (governance).

2. Requirements

ID Requirement
REQ-REL-001 Versioning is SemVer, tags vX.Y.Z. During 0.x, breaking changes are permitted with a minor bump + CHANGELOG entry (Charter §7.5). From v1.0, surfaces A–C are frozen (REQ-API-009); qhash64 changes are major-version events (Charter §7.4).
REQ-REL-002 Branching is trunk-based: protected main, short-lived PR branches, release tags on main. No long-lived release branches before v1.0; post-1.0 patch releases may branch from tags.
REQ-REL-003 The release process is the fixed checklist of §5, executed via release.yml (REQ-CI-009) with manual publication. Every step's evidence lands in docs/releases/gates/ (REQ-MS-002).
REQ-REL-004 Release artifacts: GitHub source archive, amalgamation pair (quiver.h + quiver.cpp, from M8), SHA256SUMS, artifact attestation (REQ-SEC-006). Amalgamation artifacts are release-only, never committed (REQ-REPO-011).
REQ-REL-005 Release notes per REQ-DOC-010 template for every tag.
REQ-REL-006 Version ↔ milestone mapping is fixed per §4; a version shall not ship before its milestone gate passes (REQ-MS-001).
REQ-REL-007 v1.0 ships only when: M10 gate passes; the charter §9.1 v1.0 items hold (Tiers A+B frozen, AVX-512 + dispatch complete, ledger ≥5 µarchs); the freeze audit (18 M10) is clean; zero disabled tests; regression policy clean vs v0.6.
REQ-REL-008 Post-1.0 deprecation: [[deprecated]] + one full minor version coexistence + migration notes (04 §7); removal only at a major version.

3. ADR-024 — Release and branching strategy

  • Status: Accepted. Context: solo maintainer (OA §10), boring-on-purpose (T8), charter SemVer commitment. Problem: choose branching and release mechanics that keep every mainline state releasable with one maintainer. Constraints: milestone-gated releases (REQ-MS-001); charter §7.5 SemVer rules; no long-lived branch divergence is tolerable at a bus factor of one. Alternatives: GitFlow (rejected: ceremony without a team), release trains (rejected: milestone-gated releases fit a contract-driven plan better). Decision: trunk-based + milestone-tagged releases + manual publication of CI-built drafts. Consequences: every merge to main is releasable by construction (master prompt Part 11 repository-evolution rule). Reconsideration: multi-maintainer future. Related: REQ-REL-001..003.

4. Version progression

Version Milestone API maturity Benchmark/ledger maturity Known limitations recorded
v0.1 M3 Tier A + Surfaces B/C, 0.x-fluid family benches validate; no ledger scalar only; no SIMD claims
v0.2 M4 unchanged AVX2 + autovec-avx2 variants measured x86-explicit only; no ledger publication
v0.3 M5 unchanged ledger v1, 3 µarchs; verdicts live Tier B absent; AVX-512 absent
v0.4 M6 + Tier B Tier B grids; qhash64 frozen AVX-512 absent
v0.5 M7 unchanged all four tiers measured packaging absent
v0.6 M8 unchanged pipeline bench pre-freeze API fluidity ends here in practice
v1.0 M10 frozen A–C ≥5 µarchs; regression-clean per release notes

5. Release checklist (fixed)

  1. Milestone gate record complete (REQ-MS-002). 2. ci.yml + nightly suites green on the release SHA. 3. Regression subset vs previous release on ≥2 registered machines; deltas explained (11 §9). 4. CHANGELOG + release notes reviewed. 5. Docs site builds; verdict blocks current (REQ-LEDGER-011). 6. release.yml artifacts + checksums + attestation verified. 7. Manual publication. 8. Post-release: version bump PR, gate file archived.

6. Acceptance criteria / traceability